Project Details:
Construction of Landfill Gas Powerplant
Site | Lot 2958,2959, & 1598 Tuan Mee Estate, Kuala Selangor | ||||
Project Name | JANA 3 | JANA 4 | JANA 5 | JANA 6 | JANA 7 |
Area Size | 160 acres | 160 acres | 160 acres | 160 acres | 160 acres |
Capacity | 1 MW | 1 MW | 1 MW | 1 MW | 1 MW |
Installed Capacity | 1.065 MW | 1.2 MW | 1.2 MW | 1.2 MW | 1.2 MW |
Feed-in Tariff Commencement Date | 1 September 2015 | August 2018 | Expected in January 2021 | ||
Status | Construction completed and in operation | Under construction | |||
Effective Period | 16 years from FiT Commencement Date | 21 years from FiT Commencement Date |